First 12 Jackets of East Anglia ONE Installed

Van Oord is currently running its installation campaign at East Anglia ONE wind farm in the UK.

Official Press Release Van Oord:

Jackets installation campaigns at East Anglia ONE wind farm

Last week Van Oord started its next campaign to install jackets at the East Anglia ONE wind farm. The wind farm’s 102 three-legged jacket foundations will be installed at depths of down to 55 metres in the southern North Sea, located 45 kilometres southeast of Lowestoft, UK.

ScottishPower Renewables commissioned Van Oord to function as the contractor for this project, responsible for transport and installation of the offshore wind turbine foundations, including logistics and deployment of the equipment. Currently 12 jackets have already been successfully installed on the pre-installed piles. East Anglia ONE will... ... More: Official Press Release Van Oord

Keywords:
Van Oord, jacket, installation, UK, wind farm, offshore, East Anglia ONE, three-legged







Thematically suitable Windfair.net members in the business directory

  • Newlist_logo.overspeed
  • Newlist_logo.weigt
  • Newlist_prysmian_logo_rgb
  • Newlist_anemos_logo_neu
  • Newlist_woelfel_logo
  • Newlist_rts_wind_ag_logo_652x312px
  • Newlist_ts_logo_rgb
  • Newlist_minimax_logo
  • Newlist_bmu_logo
  • Newlist_dynamica_ropes_logo_600x200

more results



Keyword Search

© smart dolphin Gmbh 1999 - 2024