Global Wind Service Half Way Trough in Serbia
Official Press Release GWS:
Global Wind Service crosses half way point at Alibunar Wind Farm in Serbia
On the weekend Global Wind Service (GWS) crossed the half way point at Alibunar Wind Farm in Serbia when a team of GWS technicians successfully completed the installation of turbine number 12 out of a total of 21.
Senvion awarded GWS with unloading, pre-assembly and installation of the 21 Senvion MM100 turbines. Work commenced at site at the 1st of February with the onloading of the components. “We are very happy to be working on this project with Senvion in Serbia, thereby elaborating and further strengthening GWS’ engagement in the country’s wind industry, following the establishment of our local business unit in 2017.” said Michael Høj Olsen, GWS Chief Commercial Officer. Alibunar wind farm is located between... ... More: Official Press Release GWS