2024-12-23
https://w3.windfair.us/wind-energy/news/22406-khobab-wind-farm-strives-for-industry-first

News Release from windfair.net

List_windfair_logo_pos

Wind Industry Profile of


Khobab wind farm strives for industry first

Khobab Wind Farm has announced the completion of its first foundation pour on 30 June 2016. The foundations are designed using an 89% replacement of cement, one of the world’s lowest carbon wind farm foundation footprints, making use of the same formulation that its sister farm, Loeriesfontein Wind Farm, successfully used in the completion of its foundations. “We are currently testing an even higher cement replacement formulation and hope to achieve the desired strength test results soon,” explained Kevin Foster, Project Manager for Khobab Wind Farm.

Situated in the Hantam Municipality, 60km north of Loeriesfontein in the Northern Cape, Khobab Wind Farm is currently employing over 100 local workers on site.  All 61 foundations are due for completion by mid December 2016.

Khobab Wind Farm is utilising extremely low quantities of Portland cement in the concrete formulation of its wind turbine foundations.  “This revolutionary formula has been tested in the adjacent wind farm and we are confident to continue to use it in our foundations.  The insights gained have allowed us to continue to test lower levels of Portland cement” said Foster.

The bases use a unique design comprising 35kgs of high grade Portland cement per cubic meter, almost 90% less than a standard concrete mix.  This composition means that the wind farm’s carbon footprint is reduced to approximately 90.7kg of carbon dioxide per cubic meter. Ground Granulated Corex Slag (GGCS), a by-product from the iron industry, is used to replace 89% of the cement.  “Cement manufacturing is typically a high energy intensive process; so by substituting the cement with a by-product the carbon footprint has been considerably lowered,” continued Foster.

A twenty-eight day compressive strength test was completed when the formulation was originally tested; it indicated that the 89% replacement ratio achieved an impressive strength of 55MPa (megapascals), and an expected ultimate strength of 100MPa, within a fifty-six day period. “The strength of concrete is measured in megapascals; theoretically a cubic metre of concrete that is rated 30 MPa, is able to withstand the weight of six bull elephants, whereas these foundations are able to withstand the approximate mass of 20 bull elephants standing on a square centimetre of concrete – a phenomenal feat,” demonstrated Cyril Attwell, Murray & Roberts Construction, Group Concrete & Research Manager.

A carbon footprint is defined as the total amount of greenhouse gases produced to directly and indirectly support human activities, expressed in equivalent tons of carbon dioxide (CO2). “The achieved reduction in our carbon footprint is phenomenal, especially considering that a standard 30MPa concrete as supplied by the ready-mix industry equates to a carbon footprint of approximately 300kgs to 350kgs of CO2 per cubic meter,” added Foster.

Traditionally, 30 MPa concrete requires between 300kg and 350kg of ordinary cement per cubic metre. But now scientists working for Murray & Roberts have developed a technology that meets the 30 MPa standard using just 25kg of cement or even less. Not only does it meet the standard, it far exceeds it. To date strengths of up to 52 MPa have been achieved on other sites using Murray & Roberts’ patented ARC (Advanced Recrystallisation) technology and 0kg of Portland cement per cubic metre.

Khobab Wind Farm is situated within the Hantam Municipality and will comprise 61 wind turbines each with an output of 140MW and will generate approximately 563,500 MWh/year of clean, renewable energy to the national grid. The wind farm will avoid approximately 550,000 tonnes of carbon emissions each year when compared to traditional fossil fuel power plants and generate enough to power around 120 000 average South African households.

The site, which spans a total of 3,200 hectares, was chosen for its excellent wind resource, favourable construction conditions and straightforward electrical connection into Eskom’s Helios substation. The wind turbines will be supplied by world-leading manufacturer Siemens Wind Power, with the blades, hubs and nacelles that compose them arriving from overseas at a nearby port and being transported by road to Loeriesfontein.  The majority of the 99m turbine towers are to be manufactured by GRI, in Atlantis, in the Western Cape. Civil and electrical works are to be completed by a consortium comprised of Murray and Roberts Construction and Consolidated Power Projects.

The Khobab Wind Farm is part of the South African Government’s Round 3 Renewable Energy Independent Power Producer Procurement Programme (REIPPP) is expected to be operational by December 2017.

Source:
Mainstream Renewables
Link:
www.mainstreamrp.com/...



All news from windfair.net

List_windfair_logo_pos

news in archive





Keyword Search

© smart dolphin Gmbh 1999 - 2024