Posted by: Windfair Editors
DEME Hits Halfway Mark on Foundation Installation
Official Press Release DEME Offshore:
Halfway mark on foundation installation at Borssele 1 & 2 Offshore Wind Farm with record installation cycles
DEME Offshore is making strong progress with the foundation installation at Ørsted’s Borssele 1 & 2 Offshore Wind Farm in the Dutch North Sea, reaching the halfway mark. Having started construction works with offshore installation vessel ‘Innovation’ in mid-January 2020, foundation installation has hit the halfway mark, with 47 out of a total of 94 foundations installed.
Despite significant weather downtime in February the installation of the foundations is on schedule for completion in early June. The large carrying capacity of ‘Innovation’, efficient jacking operations and smooth offshore bolting operations lead to record installation cycles. “Together with Ørsted, we will continue our excellent partnership for the remaining foundations. I... ... More: Official Press Release DEME Offshore
- Keywords:
- DEME Offshore, halfway, foundation, installation, Dutch, Netherlands, North Sea, Borssele, wind farm, offshore