Posted by: Windfair Editors
First Foundation in at Kriegers Flak
Official Press Release Jan De Nul:
First foundation for the offshore wind farm Kriegers Flak installed in Denmark
This weekend, the first Gravity Based Foundation for the offshore wind farm Kriegers Flak was installed in Denmark, another milestone in this project.
It concerns a 8,000 tonnes GBF which was floated off the semisubmersible barge and towed to the installation location where the heavy lift vessel Rambiz in combination with an in-house designed ballast module set the structure down onto the seabed. The second GBF, weighing 10,000 tonnes, will be installed as soon as possible, depending on the weather conditions. Once the foundations have been installed the most recent multipurpose vessel of Jan De Nul, Adhémar de Saint-Venant, will start with ballasting and scour protection works. Both foundations were constructed by Jan De Nul Group... ... More: Official Press Release Jan De Nul
- Keywords:
- Kriegers Flak, Denmark, Jan De Nul, foundation, Smulders, gravity base