Nordergründe Transmission Link Finished

Via this offshore grid connection, the correspondent wind farm will be able to bring 111 MW of renewable energy to the German mainland.

Official Press Release nkt cables:

NKT has delivered cable system for the offshore grid connection Nordergründe

Wind Industry Profile of
NKT has delivered cable system for the offshore grid connection Nordergründe

NKT has successfully commissioned and handed over the 155 kV high-voltage AC Nordergründe offshore wind transmission link on time to the Dutch-German transmission system operator TenneT.

Via this offshore grid connection, the correspondent wind farm will be able to bring 111 MW of renewable energy to the German mainland.    The Nordergründe wind farm, located in the North Sea off the coast of Germany, is part of Energiewende, the German government´s strategy to increase the share of renewable energy in Germany’s energy mix. NKT has now successfully commissioned the 155 kV  high-voltage cable system which will transmit enough offshore wind energy to cover the electricity needs of more than 100,000 households. The energy... ... More: Official Press Release nkt cables

Keywords:
nkt cables, Nordergründe, offshore, grid connection







Thematically suitable Windfair.net members in the business directory

  • Newlist_logo.drakawind

more results



Keyword Search

© smart dolphin Gmbh 1999 - 2024