2024-12-23
https://w3.windfair.us/wind-energy/news/24680-veja-mate-offshore-north-sea-germany-milestone-installation

One Half Up, One To Go

German offshore wind farm Veja Mate reaches halfway installation milestone

Official Press Release Veja Mate :

Veja Mate reaches halfway installation milestone

Veja Mate Offshore Wind Farm is pleased to announce the installation of 34 of its 67 WTGs two and a half months ahead of the schedule agreed at Financial Close in July 2015.

WTG installation began on 10th of January 2017 and as of today, 30 of the 34 WTGs are fully commissioned producing power successfully. This achievement was possible due to the relentless hard work of our Installation, WTG and Regulatory Teams and the collaboration of the German BSH, TenneT, Siemens Wind Power and its sub-contractors. Tonni Bager, Installation Package Manager stated “Being halfway in our installation campaign two and a half months ahead of schedule is a major feat owed to careful planning and daily attention to every detail. Thomas Gellert, Deputy EPC Director and WTG Package... ... More: Official Press Release Veja Mate

Keywords:
Veja Mate, offshore, North Sea, Germany, milestone, installation







Related News

Thematically suitable Windfair.net members in the business directory

  • Newlist_logo.weigt
  • Newlist_windhunter_academy_logo
  • Newlist_rts_wind_ag_logo_652x312px
  • Newlist_logo.schraubenwerk
  • Newlist_minimax_logo
  • Newlist_bwts_logo_2021
  • Newlist_woelfel_logo
  • Newlist_dynamica_ropes_logo_600x200
  • Newlist_deutsche_windtechnik_logo
  • Newlist_radolid_logo
  • Newlist_stiftung_offshorewind
  • Newlist_logo_2019_mit_signe
  • Newlist_logo.hawart
  • Newlist_logo.mesalands
  • Newlist_logo.pes

more results



Keyword Search

© smart dolphin Gmbh 1999 - 2024