Siem Offshore Contractors (SOC) has wired Veja Mate ahead of schedule

All 73 inter array cables are already installed 10 weeks before the originally calculated date.

Since October 2016, two ships from Siem have been working off the German North Sea coast to wire the Veja Mate offshore wind farm. They had been able to withstand the harsh weather conditions of up to 3 meters of waves in the winter.

The workers have successfully completed more than 10,000 person transfers to the foundations of the plants and the substation via the gangway "Walk to Work". The cable connection and test works will be continued in the coming weeks and will also be completed on schedule.

Mr. Regis Rougier, Managing Director of Siem Offshore Contractors, said: “It is a pleasure to confirm the successful completion of another project ahead of schedule, our third project utilising the “Siem Duo”. The offshore crews of the Siem Aimery and Siem Moxie as well as the onshore project team have made us proud again by providing high quality services and workmanship! We are looking forward to the next challenges for our crews and teams on our next projects.”

Source:
Siem Offshore Contractors GmbH
Author:
Windfair Staff
Keywords:
Siem, offshore, Veja Mate, inter array



All news from windfair.net

List_windfair_logo_pos

news in archive





Keyword Search

© smart dolphin Gmbh 1999 - 2024